Import resources from one project to another in version 2.8.10

Dear Users,

I am new to Ganntproject and I downloaded the version 2.8.10. In tutorials using older versions I noticed that there was a function to import resources from one project to a new one. In my version this option has disappeared. Is there another way to get the resources from an other project?

Project > Import > GanttProject files

It imports both tasks and resources.

Thank you very much!
This was easy thanks! It is just a bit weird that I can not only import resources. I tried the 3 different options but the tasks were always additionally imported.
Btw. is there a fast way to add days off to every resource in case of a holiday?

We recommend creating a project with resource only if you need to import them often.

is there a fast way to add days off to every resource in case of a holiday?

Why don’t you add a holiday to the project calendar? Project > Properties > Project Calendar.