Link (started, not necessarily finished, to start) - Predecessors options

Hello!

I’d like to know to link two tasks (I mean, for a newbie user like me, to see the arrow between 2 of them), but not with the current options. For example, first task starts and finishes, and the next task starts some days before the previous one finishes. But this second one needs the first to have started, and not necessarily finished.

You can see an example of what i want in the attached image.

Any help please?

1 Like

You can set the lag period in the predecessors tab of the successor tab properties. In your case you need negative lag.

1 Like

Awesome!! That is exactly what i wanted! Thanks!

1 Like

how is that? How can I set lag?

trying to do as the photo here.

how can i do the negative lag?

It is under the Delay Tab

Successor task properties > “Predecessors” tab > Delay

1 Like