Hello,
On a schedule with a lot of parallel tasks, I would like a report to forsee the tasks coming next week (or next month, whatever…), AND in the critical path.
AFAIK, the critical path is not on an existing attribute for tasks, in GP, to be filtered by, is it?
What I did is to export to Excel, and filter on the date, and I got it… but not if the tasks belongs to the critical path, or not. Any thoughts?