Resource Chart - Colour code resources

Hi,

Is it possible to colour code individual jobs within the Resource Chart display?

At the moment when I check the Resource Chart and have a resource finish on one job, on say a Monday and then that resource starts on another job on next day. The chart shows one continuous line. I have to expand the resource to see when jobs change. Being able to colour code jobs would be very helpful.

I have searched but not found any information on this. If this has been brought up before please point me in the direction of those posts.

Regards,

N

No, sorry, task bars in the resource chart are colored according to the resource utilization.