Timeline Colour vs Resources


(Nelleke Louw) #1

Is there a way that the colour that shows in the timeline can be linked to a specific resource? Thus, if I colour something black in the timeline, how will my team know which resource/s is/are responsible for that specific task?

I hope this is clear enough.


(Dmitry Barashev) #2

At the moment colors are not associated with resources, sorry (there is a ticket for that). However, if you need to show information about assigned resources, you can print their names next to task bars. Edit > Settings > Gantt chart > Task detals


(Nelleke Louw) #3

Sposibo! / Thank you!