Unable to add `Resources` as a column to Gantt chart


(John Schuster) #1

I’ve used GP on and off over the last couple of years and now I’ve made the decision to use GP for all my project and timeline efforts. I have a new project and when I attempt to add the Resources column to the Gantt chart using Manage Columns... many of the columns, including the Resources column are greyed out and I can’t select them to add the column to the chart.

See snapshot http://pwc-lms.com/OpenStuff/GanttProject/resources-greyed-out.png


(Dmitry Barashev) #2

(John Schuster) #3

Than you so very much, yes the user interface was a little confusing but, your explanation make it very clear what to do.