Hi there,
having enthusiastically created a project gantt (9 months, 9 resources, 600+ tasks) for the last two days I now come to the conclusion there is no view that shows the effort (in hours, or days or even minutes) for a resource.
I need to report on the forecast on resources in the project as well as on the number of days performed. Whatever I try I can’t seem to find this anywhere and I need to manually calculate task by task what the effort for a resource is.
Is this possible? I can’t do this manually week by week and change after change.
Ideally this would be table that shows TASK/Resource/Effort Now we can see Task/Resource but than it stops.
Thanks