I would like to display the total load (workload) for a specific period for personnel in the Resource Chart of GanttProject. Is such a Resource Column feature currently not supported in GanttProject?
ChatGPT suggested that a function called WORK_IN_PERIOD() is inherent to the program, but it isn’t working at all. Is there any alternative solution?
You can display the total load and cost of the resources using the corresponding columns. Right-click in the table header and choose “Manage columns…” from the context menu to open the column manager.