Hiya. I’m using GanttProject 2.8.5 Pilsen (build 2179)
I have a 4 day task assigned 100% to Bob. OK takes 4 days on Gantt chart. Add Sam 100% as a 2nd resource to the task. Still takes 4 days? Am I missing something?
Thanks!
Hiya. I’m using GanttProject 2.8.5 Pilsen (build 2179)
I have a 4 day task assigned 100% to Bob. OK takes 4 days on Gantt chart. Add Sam 100% as a 2nd resource to the task. Still takes 4 days? Am I missing something?
Thanks!
Thanks Dmitry. I read this: http://www.kvens001.students.digitalodu.com/wp-content/uploads/2015/10/ENGL-334_Project-2_GP-Quick-Guide_KVensland.pdf
Step 14 is what I want to do but it doesn’t work, just to be clear.
Is the workaround to create 2 tasks each assigned to a specific person and with a common milestone?
Cheers!_
If you mean this:
Adding more than one resource to a task will shorten the duration of that task.
then it seems to be a fantasy of the guide authors. It has never worked this way. Task in GanttProject won’t change its duration because of (un)assigning any resources.