I have added a couple of tasks, defined dependencies. I cannot however see any critical path or baseline checkbox or option in the Gantt tab.
I’m new to GanttProject, so most likely I’m doing something wrong, but cannot figure out what it is. Help is appreciated.
v3.2.3247, Desktop, Win10.
BB
Did you try restarting GP after installing updates?
1 Like
Yet another restart helped! Thank you!!