Changing calendar from days to weeks?


#1

My Gantt chart covers a large number of days and it would make the display much easier if I could change the granularity across the top to weeks. Can this be done?

I would still like to keep the task input in days, just want to compress the output by selecting weeks.


#2

I see that visually you can use the Zoom out function. Is there any other way?


(Dmitry Barashev) #3

Sorry, is anything wrong with zooming out? Why looking for other ways?


#4

That works for display, but some projects have data in weeks/months and it would be nice to input in different time units.


(Dmitry Barashev) #5

Day is the only time unit for task durations, sorry.