Changing timeline: From absolute (e.g. May) to relative time (e.g. Month 1)


#1

Hey guys,

I am new to the forum and software (2.8.5 Pilsen). I want to change my timeline from showing years and months in absolute time format e.g. 2018 May, June, July…, I just want Month 1, Month 2, Month 3 etc…


Can someone of you tell me where to make the settings, or at least a workaround?

kind regards
Slev1n


(Dmitry Barashev) #2

This feature is not supported, sorry. However, what’s the use case?


#3

Thank you for your answer. I am writing a proposal and the project start is not known yet, so the project sponsor asked for this kind of layout.


(Dmitry Barashev) #4

So it seems like starting project in January of year 1 (literally, 0001 AD) might be a good workaround. You can move the whole project to any date when dates become more certain.