Concurrent Tasks

Hi. As a completely new user, I hope I’m not being obtuse… I have three tasks which are not inter-dependent and can all start on the same date. But the team leader is involved in all three, and obviously she cannot work on them all at the same time. The Resources Chart clearly shows up this problem! What actually happens in practice is that she will divide her time between these tasks until all are complete. So I was wondering if GanttProject can be set to automatically extend the end date of the three tasks to reflect this?

In other words, if each task takes 5 days, the end time for all tasks will be 15 days after the start, not the 5 that the chart currently shows? Is there some setting relating to the team leader that automatically prevents her from being ‘double-booked’?

Many thanks,

Charlie.

Effort-driven scheduling is not (yet) supported, sorry.

Hi Dmitry. Thanks for your prompt reply. At least that saves me from spending time trying to work out the answer :slight_smile:
Regards,
Charlie