I want to use a capital project from last year by copy past and then change the name. Same process. I will just need to adjust date ressources. Can you tell me how to do it?
Thanks
Jack
- Open your project.
- Save it as different file
If you need to change the project name (which shows up e.g. in the reports) then Project > Properties.
If you need to shift the tasks then Project > Properties > Calendar > Move project start date
Thank you for your quick response!