Copy past an old project to create a new one

I want to use a capital project from last year by copy past and then change the name. Same process. I will just need to adjust date ressources. Can you tell me how to do it?
Thanks
Jack

  1. Open your project.
  2. Save it as different file

If you need to change the project name (which shows up e.g. in the reports) then Project > Properties.
If you need to shift the tasks then Project > Properties > Calendar > Move project start date

Thank you for your quick response!