Copy paste tasks in the same project

Hello,
I need to repeat similar task for each product in my project and they might have a different time plan, however tasks are similar or a subset.
When i copy paste, all the names of tasks are named “copy” which takes alot of time to rename.

Is there a way around it ?

Edit > Settings > Gantt Chart > Name pattern for task copies. Replace the default value with e.g. {1} to keep task name as is.

1 Like

Great :slight_smile: why don’t you put up a document with all these trick that we could use ?