Date Columns Dont Reflect Correct Dates

Since the recent upgrade, when creating a project chart, the Begin and Start dates do not change to reflect the schedule dates- but the individual tasks, when opened in the dialog box, do show the correct dates. My current projects all show a Begin/Finish date of 03/15/21 for all the tasks!
image

What is in your date format settings?

Thanks! I just found that out about 10 minutes ago! Thanks for the quick response…

A