Good morning all,
I don’t understand vacation management.
I do a test with two spots
• Task A – 10 days - beginning of the task on March 7 – resources Jean
• Task B – 10 days - beginning of the task on March 7 – resources Michel
• Jean is on leave from March 9 to March 16
In the Gantt chart ends both spots end on March 18th.
Normally task A should finish March 25th.
Is it normal or not?