Hello,
Resource chart does show assigment percentaje for each task, in its duration.
Would it be possible to export it to get that detail?
Thank you! Regards, M.
1 Like
UPDATE: The idea is to get the assignment percentaje for each day (or time interval).
In the case above,
DATE RESOURCE TASK ASSIGMENT
11 r1 t_0 100
11 r2 t_1 50
14 r1 t_0 100
14 r1 t_1 80
14 r2 t_0 50
15 … etc
That is, a break down of the resource total load by individual tasks for each day?
Well…yes.
(a) “a break down of the resource total load by individual tasks for each day”. Yes
And if I get the rate for each resource, then
(b) GP would also calculate the total daily cost.
But if (b) is too complex, then let’s make a iterative approach