'Grey out' completed (100%) task lines?

Greets – as I’ve said elsewhere – Gantt Project is proving to be an excellent tool. Kudos to Dmitry and the team as they develop forward.

Question (or maybe enhancement request). Is there a way to ‘grey’ the line associated with a completed task (100%)? That is, shade the entire line (the text, and the gant-bar area) when a task reaches 100% – this facilitates very rapid visual keying on the remaining tasks.

–Will

This is probably the most relevant:

At the moment you can try using “Alerts” column in the task table which shows yellow and red triangles if task is NOT yet completed (yellow) and due date is past (red). This is not exactly like hiding completed, but it kinda attracts attention to some tasks which are likely to be important.

Right-click in the task table header to access column manager.

Got it. Will give alerts a try and see how the eyes adapt.

Re the “Option to hide completed tasks”: perhaps augment the issue? It would be helpful to effectively have two independent toggles (either or both can be applied) that allows greying and/or hiding of the completed tasks.

Rationale: hiding complete tasks yields the most concise view of remaining work; but greying allows these tasks to be seen in context – which can be very helpful in dynamic projects where tasks are changing in scope and being redefined.