How to add vaccation for every ressources ? (startdate → enddate)
If a task is scheduled, how to take in account a vaccation day of ressources? (vaccation day seems to not postpone the task duration ?
How to add vaccation for every ressources ? (startdate → enddate)
If a task is scheduled, how to take in account a vaccation day of ressources? (vaccation day seems to not postpone the task duration ?
Vacation days do not affect task durations, sorry.
argg.., It’s sad, so you have to manually extend all the affected tasks of each resource?