I'm quite confused upon the Resource Payment Rate


(SkildX) #1

How is the standard rate being calculated? Is it by hours, or days? I am quite confused since I don’t see any option changing the rate type. Thanks!


(Dmitry Barashev) #2

Atomic time unit in GanttProject is day, so payment rate is per day.