Individual paid off not shown in gantt and not took in account

When I set a paid day off for a resource, it seems that the day is not counted towards the task duration and is not displayed

Days off are not accounted in the task duration, sorry.

Hi ok it’s sade, but will it be a future feature ?
How can I find a by pass solution ?

I wish it was there long time ago, but unfortunately it is pretty complicated feature. Hopefully, it will be implemented at some moment.