Hi, I’m using 3.3.3316. I’ve noticed that when creating a new task (task2) and linking it to the predesessor (task1) via end/begin (hard link), task2’s start date does not change but stays at its creation date (project start date). A ‘link-arrow’ is displayed, but the date does not change.
It feels like … the ‘dependency solving routine’ is not running, if that makes any sense.
Any ideas what I can do to solve that? Means: When linking tasks their dates change according to the new constraint?
Thanks in advance!
/edit 2026-02-04
The above remains unchanged on Win11. But I’ve doublechecked the same version on Linux. There the behaviour is as expected: If two tasks are linked, the following task’s begin date is changed to the date immediately after the first’s end date AND the task’s rendering in the gantt-chart ‘jumps’ to the new date.
Is there a setting, that I’m missing, that prevents the following tasks from being updated?
thx