Linking tasks by color from the gantt chart to the resources chart

Is it possible to link the same color from the task in the gantt chart to the allocated resources on the resource chart? you could then open your resource chart and see which projects/tasks they are assigned to by color and when.
Thanks

Color of “tasks”, in Resouce tab changes according to the level of load assigned to the resource, AFAIK.

yes thanks, is there a way to change that to match the tasks color scheme?

No such option, sorry.

no worries, thanks for getting back to me