Hello,
I have project1.gan, with baseline data “baseline1”.
I have project1_fork.gan.
How could I get baseline data “baseline1” be imported to second project file project1_fork.gan?
Would it be enough to just copy the baseline1 data into the XML?
Hello,
I have project1.gan, with baseline data “baseline1”.
I have project1_fork.gan.
How could I get baseline data “baseline1” be imported to second project file project1_fork.gan?
Would it be enough to just copy the baseline1 data into the XML?
Would it be enough to just copy the baseline1 data into the XML?
Do you mean in a text editor? Yes, it should work, provided that task identifiers match.