Hi,
If a task is scheduled for 3 weeks :
if the 1st weeks one ressource is affected 100% and start another task in parallal @ 30% on the 2nd week, how to modulate the % on the 2nd week to avoid to have 130% on the 2nd week ?
I don’t want to have to split originals tasks on several sub-tasks to match de max of 100% …