Hi, I’ve created a calendar in Apple Calendar with statutory holidays and exported it as an .ics file. When I come to import it into GanttProject, it shows up as grey and won’t import.
I’m using GP 2.8.11 on a MacBook Pro with Catalina.
I’ve imported the .ics file into my project but when I check on the chart itself, it’s affecting more dates than I’ve specified.
So, for example, Thanksgiving (Oct 12, 2020) is fine, but over the Christmas holiday, I specified Dec 25 and Dec 28, plus Jan 1 for New Years Day. However, if I insert an 8-day task to start on Dec 21, instead of finishing on Jan 4 (which I would expect), it’s finishing on Jan 6.
Ah, I see. Every holiday after importing becomes 2 days. Apparently there is a bug in the importer which makes the event end date inclusive instead of exclusive. We’ll fix that too, thanks for reporting.