Question about project calender

Hi,

I like to add our company holidays into teh project calender but I have to add every single day separately.
Is there a way to add holidays from xxx to yyy?

Best regards,
Roland

Not such option at the moment, sorry.

@RJohe To add a lot of days to the calendar section (for adding either »real« or bank holidays) I prefer to open the .gan file in a text editor (plain text editor like VSCode, BBEdit …) and add them in the XML. This looks like this:

Cheers,
Tobias

Thanks a lot!

Best regards, Roland