Recalculate the ID of activities

Is there any posibility to recalculate the ID of the activities in GanttProject ?

Regards,
Zoli

No. What’s the point of recalculating pretty meaningless identifiers?

Thank you for your reply, it is not important, most likely an OCD kind of thing than something paractical :slight_smile: but
I thought maybe there is a way, and of course I am interested in bulk kind of approach when I can modify all ID’s to get them in order.

All the best,
Zoli

If your intention is to get human-understandable identifiers which can tell something about tasks, you may want to use column “Outline number”. It is hierarchical task identifier which updates automatically as tasks move around.

1 Like

It will be really great if you could define “Predecessor” as an “Outline number” not as a “ID”. Is it possible?