Recurring work patterns (Calendar) & resource loading & costs

Hi there,

Gantt Project has been really useful, however with many staff now on part-time is there any way that each resource can have recurring events applied such as having 2 days per week non-working or having Friday non-working every two weeks etc. This is much more preferable than adding the non-working dates manually for each resource.

Secondly, I think I have found some errors in project cost and resource loading in v3.0.3002 - I don’t have the time to reproduce just yet but I am reasonably certain it is related to copying a group of existing tasks and then pasting and modifying them for re-use in the same Gantt. I am certain they are errors as I exported all the data to Excel and added up the resource utilisation and costs there and saw the same differences.

Cheers

Sandy

Existing (and pretty old) enhancement request about the resource calendars:

With respect to cost/loads, we need a reproducible scenario.