Hi,
I have next scenario and I don’t know if I’m working the correct way:
- I have created three tasks.
- I have indicated the start and end dates.
– Task A: 1/jan - 5/jan
– Task C: 15/feb - 20/feb - I want to have next assignment to the Task B:
– Start at “6/feb” (end date TaskA + 1 day)
– End at “14/feb” (start date TaskC - 1 day)
I’m trying to do it but the scheduler is not taking in account the first relation. It is assigning right the end date.
I’m using Gantt Project (“Pilsen”, 2.8.1) in Windows10 Pro.
Thanks a lot!
Regards,
Albert