Reschedule function needed

Just got this s/w and so far it’s great but it’s desperately in need of a reschedule option. What this would do is bring forwards all incomplete tasks, or those portions of the tasks that are outstanding, to begin on the current day.

What currently happens is that tasks behind schedule stagnate in the past unless manually dragged to the present day. Linked tasks will update their successors when manually moved, of course, but when you’re dealing with a great many tasks, a proportion of which are not linked or not strongly linked, some are in danger of being left behind and forgotten about.

Please use this ticket if you want to track this enhancement.

Yes, I saw that but wasn’t sure it was being progressed as it is four years old. Is this feature being worked on and if so, is it likely to be included in the near future? I need that function for a project later this year.

Ticket status is actual (as is usually the case with other tickets in our tracker). This feature has relatively high priority but we don’t give any promises, sorry.