Resource Names included on Task List Pane

Sorry…I found my answer!

Is it possible to add the resources next to the task list pane along with the duration, begin and end dates?

Hi rosemary, if you do a right mouse click near the top of the columns you will see a menu called “manage columns” select this. This will open up to dhow you what is available. Find the resources one, click on it and then click on show selected. This will add the column in.
Once its added, you can drag it to the position that works for you