Resources management: show allocated "Unit" in a new coloumn

Suggestion/Request on Resources chart.
I have created a General Gantt to manage resources for a bunch of projects.

For each project (with their own starting date and duration), I allocate a percent of the resource week (Unit), considering that 10% of their time is half day (considering 5 days per week, that’s enough micromanagement guys… ), so if a person spends 1 day per week on a project, I allocate 20% etc.
Then I try and see how much I am wishful thinking… and manage resource better.

In the Resources chart, once I expand the allocated tasks/projects for each resource, it would be very useful to have a “Unit” coloumn with the time percentage allocated for each tasks/project.
This would allow me to see at a glance by how much each resource is overallocated, and maybe decide which project to remove, has higher impact. etc.

I don’t really find the total load useful in this case.