Scheduler report

Hi,

How is it possible to read the scheduler report? I’m not getting it.
I’m using Gantt Project (“Pilsen”, 2.8.1) in Windows10 Pro.

Thanks a lot!

Regards,
Albert

It says what changed in your project due to changes in the way GanttProject works. I can’t give any better explanation. If you have troubles with understanding what is written there, please share the report (and optionally the project file).

Sorry. I have not explained correctly.
I have displayed never. Do you have a project example which it is displayed?

Regards,
Albert

If you haven’t ever see the report, you’re lucky. You basically don’t want to see it.
Why do you ask?

I’m asking to know when it is displayed because I’m able to reproduce it.
Maybe my plannings are perfect :blush: but I am not sure. Hehehe!

Regards,
Alberto

It is not about projects themselves, it is about changes in scheduler algorithm between different GanttProject versions. For instance, we made working “earliest begin” constraint in GP 2.8 and it could affect projects where this constrait was set but was essentially unused:
https://docs.ganttproject.biz/releases/#_scheduler_audit_and_report

We show the report to let users know that their old project was affected after upgrading to new GanttProject. People who just started using GanttProject recently are not supposed to see such reports.

Ah, ok. Thanks for your explanation.

Regards,
Alberto