maphe
January 13, 2020, 9:15am
1
Good morning,
we try to use GP to make products plan but we have many products in development, therefore we have the same name activity for each products and we must distinguish all.
I see there is a scheme number in gantt chart but not in resource diagram: how we can see automatically this column in resource diagram?
thanks.
Do you mean that you want to see task outline numbers in the resource chart?
maphe
January 22, 2020, 5:48am
4
Good morning,
Any news of my request?
Thanks
Task columns can’t be shown in the resource chart, sorry.
Tickets about this:
opened 12:40PM - 28 Jun 15 UTC
auto-migrated
Tasks
Type-Enhancement
Resources
```
Hi, I'm trying to make the following Interaction between the Ganth-Diagram a… nd
the Ressource-Diagram.
I added a Field into the Ganth Diagram.
Now I'd like to see the Content of the Field in the Ressource Diagram.
Exemple:
I've got a New Field, Called " CompanyName" in the Ganth Diagram I see now
where my operator is.
Now I go to the Resource Diagram, But I can't see or select the Filed "
CompanyName" and see where my Operator is.
How can I make something like that?
```
Original issue reported on code.google.com by `[email protected] ` on 31 Oct 2012 at 8:37
opened 12:39PM - 28 Jun 15 UTC
auto-migrated
Type-Enhancement
Resources
```
It is possible to configure Gantt chart so that task details are shown aroun… d
task bars (e.g. start/end dates or task name). However, Resource chart is not
configurable. It may make sense to introduce task options on Resource chart too
or to reuse options set for Gantt chart
```
Original issue reported on code.google.com by `dbarashev` on 3 Jul 2012 at 4:16