Hi, is there a way to set an end date that will appear as a coloured column down the sheet across every row?
End dates are different for different tasks. How can we place them in one column?
Hi Dmitry, i meant an end date for the whole project, not for a task.
Edit > Settings > Gantt chart > Project start/end dates
Thanks Dmitry, it shows a line which is based on what the gantt chart has calculated to be the end date, not a deadline end date that i can put in. I would really like to have a hard date I can put in that I know I need to work to and then if any task goes past that I need to rework the scheduling of that task.
Is this possible?