Split a task / add breaks to a task

Hi!

Is is possible to split a task so it could have some breaks?

Something like this

Thanks in advance!

No such feature at the moment, sorry.

This would be useful to me too.

This would be VERY useful… currently there’s no way to take account of holidays in the timeline, because you can’t split (or automatically elongate) a task so it takes account of holidays, like it does with weekends…

For everyone who wants to add “me too”: please add your +1 in the appropriate ticket in the bug tracker: https://github.com/bardsoftware/ganttproject/issues/134