im new in PM and also i have no programming skill. i used Gemini to create a plan for my project and write code for a .gan file to be imported in Ganttproject. it seems like every version of the code is correct, i can import it in the program , but start-date and end-date are switched between them, basically , my first task has the end date and vice-versa . what am i doing wrong ?
Please share the file.
i’ve sent you an e-mail with the file
I don’t see any emails from you in my inbox.
If you sent it as a reply to the forum message, please send it again directly. Forum software won’t forward any attachments.
intserv1.gan (18.2 KB)
here it is .
i guess ill be using excel then . thank you for your time and attention.
I think the problem is that the dependencies (depend tag) should be placed inside the predecessor task tag, not inside the successor.