Hi,
I think that there is a problem between links with main tasts. I created a strong link between two main tasks (both with subtasks) as it is shown below:
Then I shortened subtast “zadanie_8” and unfortunately second main tast have not moved as you can see:
“Refresh” did not solved the problem.
Should I change some setting? Any advice?
Thanks!
This issue is addressed in this ticket:
opened 11:35PM - 11 Sep 15 UTC
bug
Tasks
__Target-Ostrava
1. Create summary tasks Task1 and Task2 and child tasks Task1.1 and Task2.1
2. C… reate a FS-dependency from Task1 to Task2
3. Make Task1.1 longer. Task1 becomes longer and Task2 moves forward as expected
4. Make Task1.1 shorter. Expected that Task2 moves backward, actual: it stays on its place.
Everything works as expected if dependency goes from Task1 to Task2.1