Task Notes dissapeared from Gantt View 3.3

I have just updated Gantt Project to Version 3.3.3309 and the notes do not show on Gantt view.
However, if you check Task Properties, The notes are still there.
Is there a way to get them back as a Note Icon on the right of the Gantt view?
Thanks,
VQ

In GanttProject 3.3 the notes icon was moved to the table view, as requested in this issue:

It should be shown by default, however, if it is not, you can switch it on in the Column Manager dialog (click on the cog icon above the task table).

Wonderful I found it. Thanks a lot Dmitry. It is a most appropriate place for the icon… :smile: -)