Task progress in %

Hello. I added the % task progress into Gantt chart settings. But this always stays at 0%. How can I make this automated. for example if a task duration is 10 days and we are at day 5 the task progress should show 50%. Thanks

It is you who changes the task progress as it goes. We can’t judge that 50% is done just because we’re on day 5.

You can change the progress in the task properties.

It could be task is 25%. I therefore suggest you 1) save a baseline with the name “today’s date”. 2) updates the task with the new expected end date.
You controll the progress your project.
Fabio