Hello,
I have the project where we have to work 7 days per week, so weekend is a normal working days for us.
I didn’t find how to represent this in Gant chart. Please advise how to do this.
Hello,
I have the project where we have to work 7 days per week, so weekend is a normal working days for us.
I didn’t find how to represent this in Gant chart. Please advise how to do this.
Just forund how to do this myself. Right clich on the date and chose make xx.xx.xx a working day.
Project > Properties > Calendar.
May I kindly suggest to have a search on the forums for questions that might have already been answered?