When turning off milestone and changing the duration of task, the duration doesn't update

when turning off milestone and changing the duration of task, the duration doesn’t update.
duration updates in the duration field in properties but not on the visual with the boxes.
instead you must change the duration separately for it to update.

Do you mean, when you do it at the same time in the properties dialog?