Actual Start and End Dates

Hi, there. I have read the FAO and this is not addressed. In the real world, things don’t always go according to plan. Start dates normally get delayed so that contributes to the delay of a project. On the other end, actual end dates would for some reason also gets delayed. The ability to update the progress based not only on percentage of completion but also the actual start and end dates are important in showing where are the causes of delay. Will GanttProject consider to add this feature to future updates?

Best regards,
Tim

If what you really need is the ability to compare the planned dated with the actual ones, you may want to try using baselines.

1 Like

Thanks, I’ll check that out.