From email: Scheduling down to minutes required


(Dmitry Barashev) #1

This came by email

I like your tool a lot, but unfortunately I cannot use it. I require scheduling capabilities down to hours (better: minutes).

I assume, that I am not the only one having raised this request. I see, that your time format already permits displaying dates with hours and minutes. But start/end dates and durations do not allow this.

For the duration of tasks, even fractions of days would be sufficient (e.g. 0.5 days).


(Dmitry Barashev) #2

This problem was discussed here a few times. Please see discussions:


and ticket in the issue tracker: https://github.com/bardsoftware/ganttproject/issues/225


(Marco Cavallini) #3

Hi to all,
I’ve solved this issue using the percentage of use of the resource.
i.e. considering normal working day about 8 hours, one hour is 15%; 15min are considered 0.5%.
You can add info on the activities by new fields ( I’m managed this for internal and customer due date that should be diferent from the end of the activity).
Regards

MC