SPLIT and BRAKE TASK -same gant chart

Hi, my first time using this software.

My problem is:

  1. How can we create a chart having more than one project running simultaneously as in this link?
    https://www.google.com/search?rlz=1C1NDCM_enMY794MY794&biw=1366&bih=637&tbm=isch&sa=1&ei=75_2Wo63Hcjy8AWTrZvgCQ&q=primavera+p6&oq=primavera+p&gs_l=img.1.1.0l10.3802.6288.0.7310.2.2.0.0.0.0.160.307.0j2.2.0…0…1c.1.64.img…0.2.306…0i67k1.0.knGuy3tyW2w#imgrc=6pRu4ihspv8L5M:

two or more different projects running on the same year.

The link seems to be broken (well, not exactly broken but it shows a search of “primavera p6” images, and I am not sure what I am supposed to see on those images). Anyway, create two top-level tasks for your projects and move tasks into appropriate top-level task.

Hi, thank you for your kind reply here.

I am trying to create a SPLIT or BREAK TASK. like we are having the dotted line. How can this be done? I am new to this gantchart software. Never used any.

here is the proper link

https://www.e-education.psu.edu/geog871/l5_p5.html

here is the attached photo.

On 2017 I read no such thing exist . Just asking for now are we having it?

Breaks in the tasks are not supported, sorry. You have to create two separate tasks.

i see, but then the table is not going to be on the same level (horizon). But thanks for replying.