I have used the Export function to determine the file format for the tasks and the resources. The tasks seem to import okay but none of my attempts, and I’ve tried it probably 4 dozen times, have I been successful in importing resources.
Each time I try the import I make slight changes thinking that maybe there’s something wrong with the data’s format but I can’t even import data that I entered manually into GanttProject and exported to import back into a new blank project file.
Is there some trick or steps that I need to take first? Do all the roles need to be defined first? Doa ll the columns need to have data?
I’m running 2.8.8